This page enables you review the process of the plant's capacity planning and pull forward. 

Use the right-hand context selector to select the production plant 

Comprehensive line-format chart of Constraint Event, Hours Available, Constrained Pulled Forward Capacity Usage, Simulated Pulled Forward Capacity Usage, and Hours Needed.  

ParametersValues
Production LoadDisaggregated product demand. 
Weighted Run Rate (Per Hour)Run rate fixed in the Run rate per product page.
Hours NeededThe hours needed to satisfy the weekly demand. 
Hours AvailableTotal number of hours available at the factory for producing the product based on the Factory Calendar page. 
Net Capacity (Hours)Hours Available vs Hours Needed
Unconstrained Capacity Utilization (%)Hours Needed / Hours Available
ParametersValues
Simulated Target Usage to Pull ForwardThe system pulls forward the excess demand, so that the previous period's usage is 100%. 
Simulated Pulled Forward Capacity Usage  Hours Needed + Simulated EF Hours Pull Forward.
Simulated Max Pulled Forward Capacity Utilization (%)Simulated Pulled Forward Capacity Usage / Hours Available
ParametersValues
Constrained Pulled forward Capacity UsageBased on the finalized pull forward by the supply planner. 
Pulled Forward Capacity Utilization (%)Constrained Pulled Forward Capacity Usage / Hours Available.